Phoenix 6A-W299

Client: City of Phoenix
Architect/Engineer: Carollo Engineers
Location: Phoenix, AZ
Completion Date: 2011
Market: Municipal
Contract Amount: $2.6 M
Work Performed: Well 6A-299 is the first of many proposed ASR (Aquifer Storage and Recovery) wells located in the City of Phoenix. Weber provided design phase assistance, furnished and installed water flush turbine pump, well discharge, electrical equipment and SCADA Installation. A unique design function utilizing a VFD, control valves, and programming allows the well to transition from production pumping at 2000 gpm to recharging the aquifer at 1900 gpm without allowing air into the system.